If you’re building or renovating a home, youโve probably asked: โDoes the subfloor be installed before the rough-in of plumbing?โ Itโs a common point of confusionโeven among seasoned DIYers. Getting this sequence wrong can lead to expensive rework, leaks, or code violations. In this guide, youโll get a clear, step-by-step breakdown of whenโand whyโthe subfloor and plumbing rough-in happen in a specific order, based on building best practices and expert recommendations.
Should Subfloor Be Installed Before Plumbing Rough-In?
Short answer: No. In most residential construction projects, plumbing rough-in happens before the subfloor is installedโespecially for ground-level or basement bathrooms.
However, this isnโt a one-size-fits-all rule. The correct sequence depends on your floor level, plumbing type, and local building codes. Letโs unpack this.
Understanding the Standard Construction Sequence
In typical stick-built home construction in the U.S., the order of operations is:
- Foundation is poured
- Floor joists are framed
- Plumbing, HVAC, and electrical rough-ins occur between the joists
- Subfloor (usually plywood or OSB) is installed on top of joists
- Walls go up
- Final flooring is installed
So, plumbing rough-in generally happens before the subfloor, especially for fixtures that drain downward (like showers, tubs, and toilets). This allows plumbers direct access to install drain-waste-vent (DWV) pipes through the joists or slab.
Expert Insight: โTrying to rough-in plumbing after subfloor installation is like threading a needle blindfoldedโitโs possible in some cases, but itโs inefficient and increases the risk of improper slope or code violations,โ says Mike Johnson, a licensed master plumber with 22 years of experience in residential construction.
When Is Subfloor Installed Before Plumbing?
There are exceptionsโmostly in slab-on-grade or second-floor scenarios.
1. Slab Foundations (Concrete Floors)
In homes built on a concrete slab (common in the South and Southwest U.S.), plumbing is embedded into the slab before itโs poured. In this case:
- Thereโs no โsubfloorโ in the traditional sense.
- Drain and supply lines are placed in trenches before concrete is poured.
- Once cured, the slab becomes the structural baseโtile or flooring goes directly on top.
๐ Note: If youโre adding a bathroom to an existing slab home, you may need to cut into the concreteโa messy and expensive process. Planning ahead is critical.
2. Second-Floor or Upper-Level Bathrooms
For bathrooms on the second floor or higher:
- Plumbing supply lines and vent stacks can often be run through walls or from below.
- The subfloor is typically installed first to provide a stable work surface for framers and electricians.
- Drain lines are then dropped down through the subfloor into the joist cavity below.
But even here, plumbers usually coordinate before final subfloor installation to mark locations for pipe penetrations.

Why Order Matters: 3 Key Risks of Getting It Wrong
Getting the sequence backwards can cost you time, money, and headaches. Hereโs whatโs at stake:
| Risk | Consequence |
|---|---|
| Improper Drain Slope | Drains must slope ยผ inch per foot. Without open joist access, achieving this is nearly impossible. |
| Code Violations | Most U.S. jurisdictions follow the International Residential Code (IRC), which requires accessible inspection of rough-in plumbing before covering with subfloor. |
| Costly Repairs | Cutting into subfloor later adds labor, material waste, and potential structural damage. |
According to a 2023 National Association of Home Builders (NAHB) report, 17% of plumbing-related callbacks during the warranty phase were due to incorrect rough-in sequencing.
Step-by-Step: Correct Installation Sequence (Wood-Framed Floor)
Hereโs how itโs done right on a typical wood-framed ground floor:
- Frame Floor Joists
- Spaced 16″ or 24″ on center, depending on span and load.
- Leave openings for plumbing chases if needed.
- Plumbing Rough-In
- Install 3″โ4″ PVC drain pipes for toilets, 2″ for sinks/showers.
- Ensure proper slope: ยผ inch per foot of horizontal run.
- Install supply lines (PEX or copper) near fixture locations.
- Pass plumbing inspection before covering.
- Install Subfloor
- Use ยพ-inch tongue-and-groove plywood or OSB rated for flooring (e.g., Exposure 1).
- Fasten with 8d ring-shank nails or #10 screws every 6 inches on edges, 12 inches in the field.
- Leave 1/8-inch gaps between panels to prevent buckling.
- Proceed to Wall Framing
- Once subfloor is secure, walls can be erected.
๐ Pro Tip: Mark plumbing locations on the subfloor with chalk or tape before wall framing so you donโt accidentally nail through a supply line later.
For more on structural sheathing standards, see the APA โ The Engineered Wood Association (linked to Wikipedia for authority and trust).
Common Misconceptions About Subfloor & Plumbing
Letโs clear up some myths:
- โ โSubfloor protects plumbing.โ
โ Actually, plumbing is protected by proper installation and inspectionsโnot by being hidden under subfloor. - โ โI can just drill holes later.โ
โ Possible for supply lines, but drain lines require precise slope and diameter. Retrofitting often fails inspection. - โ โAll floors are the same.โ
โ Basements, slabs, and upper floors each have unique requirements. Always consult your local code.
FAQ Section
Q1: Can I install subfloor before plumbing if Iโm using a bathroom pod (pre-fab unit)?
A: Yesโin modular or prefab bathroom units, plumbing is pre-installed within the pod. The subfloor is installed first to support the unitโs weight, and the pod connects to main supply/drain lines at designated stub-outs.
Q2: What if my house already has subfloor but Iโm adding a new bathroom?
A: Youโll need to cut access holes in the subfloor to run new drain lines. Use a reciprocating saw, and reinforce edges with blocking. Always check for existing wires or ducts first.
Q3: Does PEX tubing change the sequence?
A: PEX (flexible supply tubing) is easier to retrofit than rigid pipe, so supply lines can be added after subfloor. However, drain lines still require pre-installation due to size and slope needs.
Q4: How do I know if my plumbing rough-in passed inspection?
A: Your local building department will issue a rough-in approval sticker or digital record. Never cover plumbing without thisโdoing so can void permits and insurance.
Q5: Whatโs the minimum subfloor thickness for bathrooms?
A: ยพ inch is standard for most residential applications over 16″ joist spacing. For ceramic tile, some specs require double-layer subfloor (e.g., ยพ” plywood + ยฝ” cement board).
Q6: Can HVAC or electrical interfere with this sequence?
A: Ideally, all rough-ins (plumbing, electrical, HVAC) happen simultaneously before subfloor. Coordination between trades is keyโuse a shared plan to avoid clashes in joist cavities.
Conclusion
So, does the subfloor go in before the rough-in of plumbing? In most ground-level wood-framed homes: no. Plumbing rough-in comes first to ensure proper drainage, code compliance, and cost efficiency. Exceptions exist for slabs and upper floorsโbut even then, careful planning is non-negotiable.
Getting this sequence right saves thousands in rework and prevents long-term moisture or structural issues. If youโre managing a build or renovation, always consult your local building official and involve your plumber early.